Goel Ganga Space Llp

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ganga Aria B1 B2P52100003739Dhanori2017Certificate Signed30 Dec 202030 Dec 2020On date
Kamal C1 C2P52100018318Dhanori2018Certificate Signed31 Dec 201930 Dec 2020+12 months
Ganga Aria AP52100019046Haveli2018Certificate Signed30 Dec 202330 Dec 2023On date
Ganga AashrayP52100029031Dhanori2021Certificate Signed31 Dec 202431 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ganga Aria B1 B2On date
  • Kamal C1 C2+12 mo
  • Ganga Aria AOn date
  • Ganga AashrayOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Kamal C1 C2 (P52100018318).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology