Goel Ganga India Pvt Ltd
Company or firm · 17 projects · 18 MahaRERA registrations
17Projects18 RERA registrations
0Completedas reported on MahaRERA project pages
82%Kept RERA date9 of 11 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 3 extended
4Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ganga Legend A4 And B1..P52100000196 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Ganga DhamP52100000212 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| Ganga Legend A3 And B3..P52100000255 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Ganga Glitz F. BldgP52100000259 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Ganga Bhagyoday D Bldg.P52100000344 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Jun 2021 | 30 Jun 2021 | On date |
| Ganga DhamP52100000393 | Pune (M Corp.) | 2017 | Certificate Signed | 30 Apr 2025 | 30 Aug 2026 | +16 months |
| Ganga Legend A2 And B4P52100021020 | Mulshi | 2019 | Certificate Signed | 31 Dec 2023 | 31 Dec 2023 | On date |
| Ganga Dham Tower C Bibvewadi PuneP52100023864 | Pune City | 2020 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
| Ganga Glitz G Undri PuneP52100024304 | Pune (M Corp.) | 2020 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Ganga Legend B2P52100024312 | Bavadhan Bk | 2020 | Certificate Signed | 31 Dec 2024 | 30 Apr 2025 | +4 months |
| Ganga Altus Kharadi PuneP52100024713 | Pune City | 2020 | Certificate Signed | 30 Dec 2028 | 30 Dec 2028 | On date |
| Wagholi Plotted DevelopmentP52100025560 | Wagholi | 2020 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Ganga Arcadia A BuildingP52100025978 | Haveli | 2020 | Certificate Signed | 30 Mar 2027 | 30 Mar 2027 | On date |
| Gg Town Wagholi PuneP52100026081 | Wagholi | 2020 | Certificate Signed | 30 Jun 2027 | 30 Jun 2027 | On date |
| Gg Town Wagholi Phase B Building 8 And 9P52100026847 | Haveli | 2020 | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
| Ganga Altus Wing FP52100027194 | Pune (M Corp.) | 2020 | Certificate Signed | 30 Jun 2028 | 30 Jun 2028 | On date |
| Ganga Legend CommercialP52100028153 | Bavadhan Bk | 2021 | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
| Ganga Legend Building B6P52100045900 | Bavadhan Bk | 2022 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
Show all 18 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 18 registrations
Track record notes
- 9 of 11 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 16 months, for Ganga Dham (P52100000393).
Regulatory cases across projects
- DeregisteredDeregistered: WAGHOLI PLOTTED DEVELOPMENT · Wagholi Plotted Development · P52100025560
- DeregisteredDeregistered: GG TOWN WAGHOLI PHASE B BUILDING 8 AND 9 · Gg Town Wagholi Phase B Building 8 And 9 · P52100026847
- DeregisteredDeregistered: GG TOWN WAGHOLI PUNE · Gg Town Wagholi Pune · P52100026081
- DeregisteredDeregistered: GANGA ALTUS WING F · Ganga Altus Wing F · P52100027194
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology