Godrej Skyline Developers Private Limited
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as Godrej Skyline Developers Limited
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mamurdi MHADA NorthP52100024142 | Haveli | 2020 | Certificate Signed | 30 Mar 2024 | 30 Mar 2027 | +36 months |
| Godrej Wood ParkP52100028133 | Haveli | 2021 | Certificate Signed | 30 Nov 2023 | 30 Nov 2023 | On date |
| Godrej SereneP52100047405 | Mamurdi | 2022 | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 months |
| Sparkle At Godrej SereneP52100048467 | Mamurdi | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 36 months, for Mamurdi MHADA North (P52100024142).
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: MAMURDI MHADA NORTH (Regulatory Case No. 375 OF 2025) dated 05 June, 2025. · Mamurdi MHADA North · P52100024142 · 5 Jun 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology