Godiva Properties Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kohinoor World Tower Phase 1P52100028796Haveli2021Not reported30 Jun 2026—On date
Kohinoor World Tower Phase IIP52100066551Chinchwad2024Not reported31 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kohinoor World Tower Phase 1On date
  • Kohinoor World Tower Phase IIOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology