Glider Buildcon Realtors

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
South TowerP51900015854Mumbai City2018Not reported30 Dec 2025—On date
Central Tower - Tower 2P51900016482Mumbai City2018Not reported30 Jun 2026—On date
North Tower - Tower 3P51900021057At Mumbai City2019Certificate Signed30 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • South TowerOn date
  • Central Tower - Tower 2On date
  • North Tower - Tower 3+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for North Tower - Tower 3 (P51900021057).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology