Girijapati Developers

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+36 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Urban VillageP52100004861Baramati (M Cl)2017Not reported23 Jul 201922 Jan 2021+18 months
Urban Village Row HousesP52100031216Baramati Rural2021Not reported23 Jul 202431 Dec 2028+53 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Urban Village+18 mo
  • Urban Village Row Houses+53 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 53 months, for Urban Village Row Houses (P52100031216).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology