Gio Properties
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+5 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| VindhyagiriP51800034813 | Borivali | 2022 | Not reported | 25 Feb 2025 | 31 Dec 2025 | +10 months |
| MatrusmrutiP51800055075 | Pahadi-Goregaon | 2024 | Not reported | 1 Oct 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 10 months, for Vindhyagiri (P51800034813).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: MATRUSMRUTI (Regulatory Case No. 402 OF 2025) dated 15 Sept, 2025. · Matrusmruti · P51800055075 · 15 Sep 2025
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology