Gini Construction Pvt Ltd
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
40%Kept RERA date2 of 5 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Bellina Phase 3P52100000902 | Lohgaon | 2017 | Not reported | 31 Mar 2019 | 30 Sep 2020 | +18 months |
| Bellina Phase 2 - CommercialP52100001305 | Lohgaon | 2017 | Not reported | 31 Mar 2018 | 30 Sep 2018 | +6 months |
| Gini Aria - Phase IP52100013814 | Haveli | 2017 | Not reported | 30 Sep 2021 | 30 Sep 2022 | +12 months |
| Gini Aria Mhada WingP52100031664 | Yawalewadi | 2021 | Not reported | 31 Mar 2025 | — | On date |
| Gini Aria - Phase 2P52100054760 | Yawalewadi | 2024 | Not reported | 30 Jun 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Bellina Phase 3 (P52100000902).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology