Gini Construction Pvt Ltd

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
40%Kept RERA date2 of 5 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bellina Phase 3P52100000902Lohgaon2017Not reported31 Mar 201930 Sep 2020+18 months
Bellina Phase 2 - CommercialP52100001305Lohgaon2017Not reported31 Mar 201830 Sep 2018+6 months
Gini Aria - Phase IP52100013814Haveli2017Not reported30 Sep 202130 Sep 2022+12 months
Gini Aria Mhada WingP52100031664Yawalewadi2021Not reported31 Mar 2025—On date
Gini Aria - Phase 2P52100054760Yawalewadi2024Not reported30 Jun 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bellina Phase 3+18 mo
  • Bellina Phase 2 - Commercial+6 mo
  • Gini Aria - Phase I+12 mo
  • Gini Aria Mhada WingOn date
  • Gini Aria - Phase 2On date

Track record notes

  • 2 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Bellina Phase 3 (P52100000902).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology