Gaurav Vishwanath Awati
Individual promoter · 10 projects · 10 MahaRERA registrations
Also appears as Mudra Realities
10Projects10 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date9 of 9 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| MadhubanapartmentP52200015569 | Shrirampur (M Cl) | 2018 | Certificate Signed | 4 Apr 2022 | 4 Apr 2022 | On date |
| Madhukosh HeightsP52200022069 | Shrirampur | 2019 | Certificate Signed | 8 Aug 2023 | 8 Aug 2023 | On date |
| Pride ParkP52200027233 | Shrirampur (M Cl) | 2020 | Certificate Signed | 11 Oct 2023 | 11 Oct 2023 | On date |
| Sai VishwaP52200032441 | Shrirampur (M Cl) | 2022 | Certificate Signed | 11 Sep 2023 | 11 Sep 2023 | On date |
| Atharva HeightsP52200033871 | Shrirampur (M Cl) | 2022 | Certificate Signed | 11 Oct 2024 | 11 Oct 2024 | On date |
| Golden LeafP52200049448 | Shrirampur (M Cl) | 2023 | Certificate Signed | 1 Nov 2024 | 1 Nov 2024 | On date |
| Dhole ComplexP52200050319 | Shrirampur (M Cl) | 2023 | Certificate Signed | 1 May 2024 | 1 May 2024 | On date |
| Mangal ResidencyP52200051562 | Shrirampur (M Cl) | 2023 | Certificate Signed | 20 Mar 2025 | 20 Mar 2025 | On date |
| Bhagirathi HeightsP52200076748 | Shrirampur (M Cl) | 2024 | Certificate Signed | 6 May 2026 | 6 May 2026 | On date |
| Ivaan TowerPM1010002500740 | Shrirampur (M Cl) | 2025 | Certificate Signed | 20 Jun 2027 | 20 Oct 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 9 of 9 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Ivaan Tower (PM1010002500740).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology