Garva Land Deal Private Limited

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Harbour City Sector-IP52000009266Dhamansai2017Certificate Signed31 Mar 201831 Mar 2018On date
Harbour City Sector-IIIP52000009913Malsai2017Certificate Signed31 Mar 201931 Mar 2019On date
Balaji Dham Phase-1P52100011371Misalawadi (Nv)2017Certificate Signed30 Mar 202331 Mar 2027+48 months
Phaltan Megacity - ResidentialP52700013055Mirgaon2017Certificate Signed31 Dec 201931 Dec 2019On date
Garva Megacity Phase IP52700032724Khandala2022Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Harbour City Sector-IOn date
  • Harbour City Sector-IIIOn date
  • Balaji Dham Phase-1+48 mo
  • Phaltan Megacity - ResidentialOn date
  • Garva Megacity Phase I+4 mo

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Balaji Dham Phase-1 (P52100011371).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology