Gangotree Homes
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 7 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| TulipP52100077644 | Kothrud | 2024 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| SiddharthP52100077732 | Erandwane | 2024 | Certificate Signed | 30 Jan 2027 | 30 May 2027 | +4 months |
| PranaliP52100080449 | Kothrud | 2025 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| VidurkrupaPR1260002500335 | Kothrud | 2025 | Certificate Signed | 31 Oct 2028 | 28 Feb 2029 | +4 months |
| ShakuntalaPR1260002501770 | Sadashiv Peth | 2025 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Preet CPR1260002502943 | Shivajinagar Bhamburda | 2026 | Certificate Signed | 30 Sep 2028 | 30 Jan 2029 | +4 months |
| Nav RahulPR1260002600558 | Erandwane South | 2026 | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Tulip (P52100077644).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology