Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Krishna IrisP51700079334Navi Mumbai (M Corp.)2025Certificate Signed31 Dec 202830 Apr 2029+4 months
Krishna Aura NXPR1270002600767Kharghar2026Certificate Signed30 Apr 203130 Aug 2031+4 months
Krishna Park viewPR1330002601551Koparkharane2026Certificate Signed30 Jun 203030 Jun 2030On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Krishna Iris+4 mo
  • Krishna Aura NX+4 mo
  • Krishna Park viewOn date

Track record notes

  • Longest extension on record: 4 months, for Krishna Iris (P51700079334).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology