Gagan Global Developers

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
MicasaaP52100004919Haveli2017Certificate Signed30 Sep 202030 Mar 2022+18 months
Kumar Palladium PlazaP52100032535Wagholi2022Certificate Signed31 Dec 202931 Dec 2029On date
MicasaaP52100054457Haveli2024Certificate Signed30 Jun 202830 Oct 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Micasaa+18 mo
  • Kumar Palladium PlazaOn date
  • Micasaa+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Micasaa (P52100004919).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology