G.T.Developers

Company or firm · 2 projects · 3 MahaRERA registrations

Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mangal VishwaP52100003611Pimpri Chinchawad (M Corp.)2017Not reported30 Dec 2021—On date
Mangal DhaaraP52100006218Pimpri Chinchawad (M Corp.)2017Not reported30 Aug 2018—On date
Mangal VishwaP52100018839Pimpri Chinchawad (M Corp.)2018Not reported30 Dec 202230 Dec 2023+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mangal VishwaOn date
  • Mangal DhaaraOn date
  • Mangal Vishwa+12 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Mangal Vishwa (P52100018839).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology