G R K Infra Developments

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Orion CornerP52000020966Vadavali2019Certificate Signed11 Nov 202211 Nov 2022On date
Aryan CornerP52000052641Dapoli2023Certificate Signed30 Apr 202730 Aug 2027+4 months
Orion HeightsP52000078672Dapoli2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Orion CornerOn date
  • Aryan Corner+4 mo
  • Orion Heights+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Aryan Corner (P52000052641).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology