Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as G K Realtors

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Radha ComplexP51800010063Kurla2017Not reported30 Jun 2019—On date
Building No. 1 - Sai Indu TowerP51800049986Bhandup2023Not reported30 Jun 202430 Jun 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Radha ComplexOn date
  • Building No. 1 - Sai Indu Tower+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Building No. 1 - Sai Indu Tower (P51800049986).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology