G.K.Builders
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as G. K. BUILDERS
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Trimurti Darshan Co Op Hsg Soc LtdP51700053427 | Ambarnath(M Cl) | 2023 | Certificate Signed | 31 May 2025 | 31 May 2025 | On date |
| Shree Ayyappa Co-Operative Housing Society LimitedP51700079960 | Badlapur (M Cl) | 2025 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
| Om Chaitanya Co-Operative Housing Society LimitedP51700080609 | Badlapur (M Cl) | 2025 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 4 months, for Shree Ayyappa Co-Operative Housing Society Limited (P51700079960).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology