Four Pillars

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Navkar TrimurtiP52100047323Pimpri Chinchawad (M Corp.)2022Certificate Signed30 Mar 202430 Mar 2024On date
Navkar AnandP52100050824Pimpri Chinchawad (M Corp.)2023Certificate Signed31 Aug 202531 Aug 2025On date
Navkar SuchitP52100053413Pimpri Chinchawad (M Corp.)2023Certificate Signed15 Jun 202615 Jun 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Navkar TrimurtiOn date
  • Navkar AnandOn date
  • Navkar SuchitOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology