Flying Earth Llp

Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed

3Projects3 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pruthvi ShantadeepP51800020800Andheri2019Completed30 Jun 2023—On date
Pruthvi PushpanjaliP51800046070Andheri2022Certificate Signed30 Jun 202630 Jun 2026On date
Pruthvi SymphonyPR1180002602097Vileparle2026Not reported31 Mar 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pruthvi ShantadeepOn date
  • Pruthvi PushpanjaliOn date
  • Pruthvi SymphonyOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology