Fifthwall Builders Private Limited
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+34 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Prashant Co-Operative Housing Society LimitedP51900008249 | Ward Abcd | 2017 | Certificate Signed | 31 Dec 2017 | 30 Oct 2020 | +34 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 34 months, for Prashant Co-Operative Housing Society Limited (P51900008249).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus M/s Fifthwall Builders Private Limited (Suo Motu Case No. 32 of 2019) dated 17th December 2019 · Prashant Co-Operative Housing Society Limited · P51900008249 · 17 Dec 2019
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology