Farrokh Framji Wadia

Individual promoter · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bluegrass Business ParkP52100021008Pune (M Corp.)2019Certificate Signed30 Jun 202630 Oct 2026+4 months
Bluegrass Business ParkP52100025080Pune (M Corp.)2020Certificate Signed30 Dec 202830 Dec 2028On date
EWS BuildingP52100031954Pune (M Corp.)2021Certificate Signed31 Dec 20233 Jan 2025+13 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bluegrass Business Park+4 mo
  • Bluegrass Business ParkOn date
  • EWS Building+13 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 13 months, for EWS Building (P52100031954).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology