Eshan Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Panvelkar PrestigeP51700028208Ambarnath2021Not reported30 Jun 2024—On date
Panvelkar Greens - Phase IP51700033348Badlapur (M Cl)2022Not reported31 Dec 202531 Dec 2026+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Panvelkar PrestigeOn date
  • Panvelkar Greens - Phase I+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Panvelkar Greens - Phase I (P51700033348).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology