Skip to content

Empress & Adishakti Jv

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
The Golf BoulevardP51800002734Kurla2017Certificate Signed30 Jun 202230 Jun 2022On date
The Golf BoulevardP51800021401Kurla2019Certificate Signed30 May 202530 May 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • The Golf BoulevardOn date
  • The Golf BoulevardOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology