Empire Properties

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+11 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Empire Square Phase IIP52100005190Pimpri Chinchawad (M Corp.)2017Certificate Signed30 Sep 202030 Mar 2022+18 months
Empire Square Phase IIIP52100056031Chinchwad2024Certificate Signed31 Dec 203030 Apr 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Empire Square Phase II+18 mo
  • Empire Square Phase III+4 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Empire Square Phase II (P52100005190).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology