Ellora Buildwell Pvt Ltd

Company or firm · 3 projects · 5 MahaRERA registrations

3Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nakshatra I LandP52100003804Pimpri Chinchawad (M Corp.)2017Certificate Signed30 Jul 201929 Jan 2021+18 months
Nakshatra I Land Phase 3P52100046609Pimpri Chinchawad (M Corp.)2022Certificate Signed30 Jun 202630 Jun 2026On date
Nakshatra i LandP52100050468Haveli2023Certificate Signed30 Dec 202629 Dec 2027+12 months
Nakshatra i LandP52100056189Haveli2024Certificate Signed30 Dec 202730 Apr 2028+4 months
Nakshatra I LandPC1264042602061Pimpri Chinchawad (M Corp.)2026Certificate Signed12 Jul 202912 Jul 2029On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nakshatra I Land+18 mo
  • Nakshatra I Land Phase 3On date
  • Nakshatra i Land+12 mo
  • Nakshatra i Land+4 mo
  • Nakshatra I LandOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Nakshatra I Land (P52100003804).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology