Ellora Buildwell Pvt Ltd
Company or firm · 3 projects · 5 MahaRERA registrations
3Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Nakshatra I LandP52100003804 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 30 Jul 2019 | 29 Jan 2021 | +18 months |
| Nakshatra I Land Phase 3P52100046609 | Pimpri Chinchawad (M Corp.) | 2022 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Nakshatra i LandP52100050468 | Haveli | 2023 | Certificate Signed | 30 Dec 2026 | 29 Dec 2027 | +12 months |
| Nakshatra i LandP52100056189 | Haveli | 2024 | Certificate Signed | 30 Dec 2027 | 30 Apr 2028 | +4 months |
| Nakshatra I LandPC1264042602061 | Pimpri Chinchawad (M Corp.) | 2026 | Certificate Signed | 12 Jul 2029 | 12 Jul 2029 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 18 months, for Nakshatra I Land (P52100003804).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology