Elite Housing Llp

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VistaP51800046797Mumbai2022Certificate Signed31 Dec 202531 Dec 2025On date
Shree Ram ResidencyP51800054905Mumbai2024Certificate Signed31 Dec 202631 Dec 2026On date
SpectrumPR1180002502121Others2026Certificate Signed31 Dec 203030 Apr 2031+4 months
Le ReposPR1180002502435Bandra2026Certificate Signed31 Dec 203030 Apr 2031+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VistaOn date
  • Shree Ram ResidencyOn date
  • Spectrum+4 mo
  • Le Repos+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Spectrum (PR1180002502121).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology