Ekta Everglade Homes Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+15 movs RERA proposed date · 1 extended
Regulatory cases3MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ekta Tripolis Phase IIP51800000731Borivali2017Not reported31 Dec 2026—On date
Ekta Tripolis Phase IP51800000947Borivali2017Not reported30 Jun 202130 Dec 2023+30 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ekta Tripolis Phase IIOn date
  • Ekta Tripolis Phase I+30 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Ekta Tripolis Phase I (P51800000947).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology