Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dp Star TrilokP51800003937Kurla2017Not reported15 Dec 202214 Dec 2023+12 months
Dp Star TriveniP51800004550Kurla2017Not reported15 Dec 202231 Dec 2024+24 months
Dp Star TrinetraP51800010455Kurla2017Not reported15 Dec 202231 Dec 2024+24 months
TrimbacP51800055483Bhandup2024Not reported30 Jun 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dp Star Trilok+12 mo
  • Dp Star Triveni+24 mo
  • Dp Star Trinetra+24 mo
  • TrimbacOn date

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Dp Star Triveni (P51800004550).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology