Dp Buildhomes Llp
Company or firm · 4 projects · 4 MahaRERA registrations
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Dp Star TrilokP51800003937 | Kurla | 2017 | Not reported | 15 Dec 2022 | 14 Dec 2023 | +12 months |
| Dp Star TriveniP51800004550 | Kurla | 2017 | Not reported | 15 Dec 2022 | 31 Dec 2024 | +24 months |
| Dp Star TrinetraP51800010455 | Kurla | 2017 | Not reported | 15 Dec 2022 | 31 Dec 2024 | +24 months |
| TrimbacP51800055483 | Bhandup | 2024 | Not reported | 30 Jun 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Dp Star Triveni (P51800004550).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology