Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Casa Grande B WingP52100005682Pimpri Chinchawad (M Corp.)2017Not reported30 Jun 202129 Dec 2022+18 months
The Unicorn Building A Wing A1 & A2PR1262022600338Ravet2026Not reported31 Dec 2030—On date
The Unicorn Building DPM1260002601012Ravet2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Casa Grande B Wing+18 mo
  • The Unicorn Building A Wing A1 & A2On date
  • The Unicorn Building DOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Casa Grande B Wing (P52100005682).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology