Disha Construction
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Datta Ramanand Chs LtdP51800001236 | Andheri | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Sat Anupa Chs Phase 1P51800001640 | Andheri | 2017 | Not reported | 31 Mar 2020 | 30 Mar 2022 | +24 months |
| Swastik Phase 1P51800002197 | Andheri | 2017 | Not reported | 31 Dec 2019 | 31 Dec 2023 | +48 months |
| Tulip Phase 1P51800024339 | Andheri | 2020 | Not reported | 30 Jan 2025 | — | On date |
| Disha ElysiumP51800077977 | Ambivali | 2024 | Not reported | 30 Mar 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 48 months, for Swastik Phase 1 (P51800002197).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology