Disha Construction

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date1 of 4 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Datta Ramanand Chs LtdP51800001236Andheri2017Not reported31 Dec 201930 Dec 2021+24 months
Sat Anupa Chs Phase 1P51800001640Andheri2017Not reported31 Mar 202030 Mar 2022+24 months
Swastik Phase 1P51800002197Andheri2017Not reported31 Dec 201931 Dec 2023+48 months
Tulip Phase 1P51800024339Andheri2020Not reported30 Jan 2025—On date
Disha ElysiumP51800077977Ambivali2024Not reported30 Mar 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Datta Ramanand Chs Ltd+24 mo
  • Sat Anupa Chs Phase 1+24 mo
  • Swastik Phase 1+48 mo
  • Tulip Phase 1On date
  • Disha ElysiumOn date

Track record notes

  • 1 of 4 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 48 months, for Swastik Phase 1 (P51800002197).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology