Skip to content
Deedo home
Menu

Dinesh Amrutlal Thakkar

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vraj DhamP51800005968Borivali2017Not reported1 Mar 201829 Feb 2020+23 months
VrindavanP51800032747Borivali2022Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vraj Dham+23 mo
  • VrindavanOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 23 months, for Vraj Dham (P51800005968).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology