Dhaval Housing Aop
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sunrise CharkopP51800004387 | Borivali | 2017 | Not reported | 30 Mar 2022 | — | On date |
| Sunrise Orlem 2B Phase 3P51800006843 | Borivali | 2017 | Not reported | 30 Jun 2022 | 31 Dec 2023 | +18 months |
| Sunrise Orlem 2A Phase 1P51800007706 | Borivali | 2017 | Not reported | 31 Jul 2022 | 31 Jan 2023 | +6 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 18 months, for Sunrise Orlem 2B Phase 3 (P51800006843).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology