Dharmesh Constructions Private Limited

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 2 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Avenue Wing AP51800002030Borivali2017Not reported31 Dec 201930 Dec 2021+24 months
Avenue Wing BP51800004402Borivali2017Not reported30 Jun 202130 Dec 2026+66 months
Avenue Wing A phase 2P51800030589Borivali2021Not reported31 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Avenue Wing A+24 mo
  • Avenue Wing B+66 mo
  • Avenue Wing A phase 2On date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 66 months, for Avenue Wing B (P51800004402).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology