Dharmesh Constructions Private Limited
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 2 extended
2Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Avenue Wing AP51800002030 | Borivali | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2021 | +24 months |
| Avenue Wing BP51800004402 | Borivali | 2017 | Not reported | 30 Jun 2021 | 30 Dec 2026 | +66 months |
| Avenue Wing A phase 2P51800030589 | Borivali | 2021 | Not reported | 31 Dec 2024 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 66 months, for Avenue Wing B (P51800004402).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: AVENUE WING B (Regulatory Case No. 307 OF 2024) dated 26 Dec 2024. · Avenue Wing B · P51800004402 · 26 Dec 2024
- Regulatory orderRegulatory order: PROJECT NAME: AVENUE WING B(Regulatory Case No.82 of 2023) dated 2 November 2023. · Avenue Wing B · P51800004402 · 2 Nov 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology