Dhanraj Harichand Khandelwal
Individual promoter · 2 projects · 2 MahaRERA registrations · 2 reported completed
2Projects2 RERA registrations
2Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vitthalarpan Residency-BP50300004073 | Amravati (M Corp.) | 2017 | Completed | 15 Aug 2020 | 15 Jan 2022 | +17 months |
| Maharshi ApartmentP50300020934 | Amravati (M Corp.) | 2019 | Completed | 30 Mar 2022 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 17 months, for Vitthalarpan Residency-B (P50300004073).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology