Devanand Narayanrao Kotgire (Huf)
Company or firm · 3 projects · 3 MahaRERA registrations · 2 reported completed
3Projects3 RERA registrations
2Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Disha Kunjban Phase 1P51500001108 | Wadgaon Kolhati (Ct) | 2017 | Completed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Disha Kunjaban Phase 3P51500001537 | Wadgaon Kolhati (Ct) | 2017 | Completed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Disha Kunjaban Phase 2P51500001997 | Wadgaon Kolhati (Ct) | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Disha Kunjban Phase 1 (P51500001108).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology