Devanand Narayanrao Kotgire (Huf)

Company or firm · 3 projects · 3 MahaRERA registrations · 2 reported completed

3Projects3 RERA registrations
2Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Disha Kunjban Phase 1P51500001108Wadgaon Kolhati (Ct)2017Completed31 Dec 201831 Dec 2019+12 months
Disha Kunjaban Phase 3P51500001537Wadgaon Kolhati (Ct)2017Completed31 Dec 201831 Dec 2019+12 months
Disha Kunjaban Phase 2P51500001997Wadgaon Kolhati (Ct)2017Certificate Signed31 Dec 201831 Dec 2019+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Disha Kunjban Phase 1+12 mo
  • Disha Kunjaban Phase 3+12 mo
  • Disha Kunjaban Phase 2+12 mo

Track record notes

  • 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Disha Kunjban Phase 1 (P51500001108).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology