Delta Developers

Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Keshao Rukhmini ApartmentP50500016600Nagpur (M Corp.)2018Not reported30 Dec 202110 Mar 2023+15 months
Shree Vinayak AppartmentP50500022368Nagpur (M Corp.)2019Not reported30 Dec 202210 Mar 2023+3 months
Sarthak PlazaP50500046859Nagpur (M Corp.)2022Not reported31 Dec 2025—On date
SaphalyaP50500047154Nagpur (M Corp.)2022Not reported31 Dec 2025—On date
Bela HeightsP50500055769Nagpur (M Corp.)2024Not reported31 Mar 2027—On date
Anant ApartmentsP50500079789Nagpur (M Corp.)2025Not reported31 Mar 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Keshao Rukhmini Apartment+15 mo
  • Shree Vinayak Appartment+3 mo
  • Sarthak PlazaOn date
  • SaphalyaOn date
  • Bela HeightsOn date
  • Anant ApartmentsOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 15 months, for Keshao Rukhmini Apartment (P50500016600).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology