Skip to content

Deepak Machhindranath Balkawade

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
PancharatnaP51600031336Sansari2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Panchmoti ResidencyP51600034357Sansari2022Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pancharatna+4 mo
  • Panchmoti Residency+4 mo

Track record notes

  • Longest extension on record: 4 months, for Pancharatna (P51600031336).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology