Davakhar Infrastructure Private Limited
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 4 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Davakhar EleganceP51700016124 | Pisavali | 2018 | Certificate Signed | 30 Dec 2022 | 31 Mar 2027 | +51 months |
| Davakhar Elegance Phase IIP51700046008 | Pisawali | 2022 | Certificate Signed | 29 Apr 2026 | 29 Apr 2026 | On date |
| Davakhar Sereno Phase IP51700077564 | Adivali Dhokali | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Davakhar Sereno Phase IIIP51700077873 | Adivali Dhokali | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Davakhar Sereno Phase III BP51700080045 | Adivali Dhokali | 2025 | Certificate Signed | 31 Mar 2030 | 31 Jul 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 51 months, for Davakhar Elegance (P51700016124).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME:DAVAKHAR ELEGANCE (Regulatory Case No.133 of 2024) dated 1 February 2024. · Davakhar Elegance · P51700016124 · 1 Feb 2024
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology