Darvesh Properties Private Limited
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+30 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mariam ResidencyP51900005018 | Mumbai City | 2017 | Not reported | 30 Jun 2021 | 31 Dec 2023 | +30 months |
| Westin Darvesh HorizonP51700005672 | Mirabhayandar (M Corp.) | 2017 | Not reported | 31 Dec 2025 | 31 Dec 2025 | On date |
| Quettawalla ResidencyP51900005346 | Mumbai City | 2017 | Not reported | 30 Jun 2021 | 31 Dec 2023 | +30 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 30 months, for Mariam Residency (P51900005018).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology