D Map Estates

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
D-Maps ShivtirthP51600080458Satpur2025Certificate Signed31 Jul 202830 Nov 2028+4 months
D-Map’s Shivtirth-BPR1221012602240Satpur2026Certificate Signed30 Sep 203130 Sep 2031On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • D-Maps Shivtirth+4 mo
  • D-Map’s Shivtirth-BOn date

Track record notes

  • Longest extension on record: 4 months, for D-Maps Shivtirth (P51600080458).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology