D A Construction
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
83%Kept RERA date5 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Om Sai RegencyP51700003660 | Ambarnath(M Cl) | 2017 | Not reported | 28 Feb 2019 | 28 Feb 2020 | +12 months |
| Om Sai TowersP51700011648 | Ambarnath(M Cl) | 2017 | Not reported | 31 Jan 2018 | — | On date |
| Om Sai HeightsP51700021733 | Ambarnath(M Cl) | 2019 | Not reported | 30 May 2024 | — | On date |
| Om Sai ClassicP51700028873 | Ambarnath(M Cl) | 2021 | Not reported | 30 Jun 2025 | — | On date |
| Aadi Arambh ShivkantaP51700047627 | Ambarnath(M Cl) | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Om Sai AvenueP51700054556 | Ambarnath(M Cl) | 2024 | Not reported | 31 Dec 2025 | — | On date |
| Om Sai PalmsPR1330002500346 | Ambarnath(M Cl) | 2025 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Om Sai Regency (P51700003660).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology