Concord Properties

Company or firm · 2 projects · 3 MahaRERA registrations

2Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aksha AmulyamP52100010533Pimpri Chinchawad (M Corp.)2017Certificate Signed26 Feb 202126 Feb 2022+12 months
Aksha AmbarP52100032442Pimpri Chinchawad (M Corp.)2022Certificate Signed31 Dec 202430 Jun 2025+6 months
Aksha AmbarP52100077655Pimpri Chinchawad (M Corp.)2024Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aksha Amulyam+12 mo
  • Aksha Ambar+6 mo
  • Aksha Ambar+4 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Aksha Amulyam (P52100010533).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology