Concord Enterprises
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+108 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Legacy VrindavanP52000012969 | Karjat | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2027 | +108 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 108 months, for Legacy Vrindavan (P52000012969).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus Concord Enterprises.(Suo Motu Case No.187 of 2020) dated 16 March 2020 · Legacy Vrindavan · P52000012969 · 18 Mar 2020
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology