Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Suraksha Smart City - Phase IP99000023396Vasaivirar City (M Corp)2019Certificate Signed30 Dec 202431 Dec 2026+24 months
Suraksha Smart City - Phase IIIP99000081050Vasai Virar City (M Corp)2025Certificate Signed31 Dec 202931 Dec 2029On date
Suraksha Smart City - Phase IIPM1242022601990Rajawali2026Certificate Signed31 Dec 203131 Dec 2031On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Suraksha Smart City - Phase I+24 mo
  • Suraksha Smart City - Phase IIIOn date
  • Suraksha Smart City - Phase IIOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Suraksha Smart City - Phase I (P99000023396).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology