Citywood Builders Private Limited

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as Citywood Builders Pvt.Ltd.

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hubtown Vedant- 14th To 18th FloorP51900000465Mumbai City2017Not reported30 Dec 202328 Dec 2025+24 months
Hubtown Vedant Ground to 2nd FloorP51900000839Mumbai City2017Not reported31 Mar 2019—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hubtown Vedant- 14th To 18th Floor+24 mo
  • Hubtown Vedant Ground to 2nd FloorOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Hubtown Vedant- 14th To 18th Floor (P51900000465).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology