City And Industrial Development Corporation Of Mahrastra Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sector 15 Roadpali KalamboliP52000017437Rodpali2018Not reported31 Mar 202130 Sep 2022+18 months
Sector 40 KhargharP52000017448Panvel2018Not reported31 Oct 202130 Apr 2022+6 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sector 15 Roadpali Kalamboli+18 mo
  • Sector 40 Kharghar+6 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Sector 15 Roadpali Kalamboli (P52000017437).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology