City And Industrial Development Corporation Of Mahrastra Ltd
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sector 15 Roadpali KalamboliP52000017437 | Rodpali | 2018 | Not reported | 31 Mar 2021 | 30 Sep 2022 | +18 months |
| Sector 40 KhargharP52000017448 | Panvel | 2018 | Not reported | 31 Oct 2021 | 30 Apr 2022 | +6 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Sector 15 Roadpali Kalamboli (P52000017437).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology