Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 3 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Plot No 63 Sector 12 DronagiriP52000017365 | Navghar | 2018 | Not reported | 31 Mar 2021 | 30 Sep 2022 | +18 months |
| Plot No 68 Sector 12 DronagiriP52000017368 | Phunde | 2018 | Not reported | 31 Mar 2021 | 30 Sep 2022 | +18 months |
| Plot No 01 Sector 11 DronagiriP52000017480 | Navghar | 2018 | Not reported | 31 Mar 2021 | 30 Sep 2022 | +18 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Plot No 63 Sector 12 Dronagiri (P52000017365).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology