Chrishh Holdings
Company or firm · 12 projects · 12 MahaRERA registrations
12Projects12 RERA registrations
0Completedas reported on MahaRERA project pages
90%Kept RERA date9 of 10 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Chrishh FortuneP52100008612 | Talegaon Dabhade (M Cl) | 2017 | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| Chrishh VasantP52100008617 | Talegaon Dabhade (M Cl) | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Chrishh SpringsP52100008928 | Talegaon Dabhade (M Cl) | 2017 | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| Chrishh HarmonyP52100009128 | Talegaon Dabhade (M Cl) | 2017 | Certificate Signed | 30 Sep 2019 | 30 Sep 2019 | On date |
| Vardhman SplendourP52100016943 | Wadagaon (Ct) | 2018 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Elite WorldP52100018325 | Talegaon Dabhade (M Cl) | 2018 | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| CrossroadsP52100022626 | Talegaon Dabhade (R) | 2019 | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Galaxy ApartmentsP52100022660 | Talegaon Dabhade (R) | 2019 | Certificate Signed | 30 Jun 2022 | 30 Jun 2022 | On date |
| Chrishh AnantP52100029265 | Talegaon Dabhade (R) | 2021 | Certificate Signed | 31 Dec 2022 | 31 Dec 2022 | On date |
| Queens CornerP52100052113 | Talegaon Dabhade (R) | 2023 | Certificate Signed | 31 Mar 2026 | 31 Jul 2026 | +4 months |
| Hill Top ResidencyPR1260002501836 | Talegaon Dabhade (R) | 2025 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Shalom HarmonyPM1260002600174 | Talegaon Dabhade (R) | 2026 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
Show all 12 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 12 registrations
Track record notes
- 9 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Queens Corner (P52100052113).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology