Choicelifestyle

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Goodwill CrescentP52100022861Mundhawa2019Certificate Signed30 Dec 202430 Dec 2024On date
Goodwill VerveP52100046076Mundhawa2022Certificate Signed31 May 202631 May 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Goodwill CrescentOn date
  • Goodwill VerveOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.