Skip to content
Deedo home
Menu

Chamunda Developers

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aadinath Complex Bldg No 1 and 2P99000012472Palghar2017Not reported31 Dec 2018—On date
Aadinath ComplexP99000020460Palghar2019Not reported30 Sep 202030 Mar 2022+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aadinath Complex Bldg No 1 and 2On date
  • Aadinath Complex+18 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Aadinath Complex (P99000020460).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology